BREAKING ๐Ÿ‡ณ๐Ÿ‡ฌ๐ŸŽ“: Former Senate President Abubakar Bukola Saraki has pledged to cover the remaining relocation costs for Adisa Blessing Oluwafikayo after the First Class UNILORIN Mathematics graduate (CGPA: 4.76/5.0) appealed for financial support despite securing a fully funded Master’s scholarship at the University of Calabria in Italy. Bandits Foiled: Hunters, Military Repel Attack on Kwara Traditional Ruler, Two Injured BREAKING: Kwara Government Takes Ex-Governor Saraki to Court Over Claim About AbdulRazaq’s Education Louisiana Man First in Region to Be Functionally Cured of Sickle Cell Disease Through Gene Editing EFCC Chair Reveals How Yahoo Boys Stole Judge’s N7.2m Child’s School Fees Overnight BREAKING: FG Summons Ivorian Ambassador Over Death of Nigerian in Custody, Demands Compensation South Africa to Nigeria: “We Will Pay No Compensation โ€“ Tell Us Where Your Drug Dens Are”
NEWS

TCN Boosts Sagamu Station with New Mega Volt

December 9, 2023 2 min read

Residents and organisations in Sagamu and other parts of Ogun State may breathe a new lease of life in power supply.

This is because the Transmission Company of Nigeria (TCN), said it had successfully energised the newly installed T3 1ร—60 Mega Volt Ampere (MVA)132/33 Kilo Volt (kV) power transformer in its Shagamu 1Transmission Substation.

Mrs Ndidi Mbah, TCNโ€™S general manager Public Affairs said this in a statement in Abuja on Friday.

Mbah said that the 96 Mega Watts (MW) 132/33kV transmission sub-station presently had the capacity to wheel 144MW with the addition of the newly energised T3 1X60MVA transformer.

According to her, the direct beneficiaries of the project were Ibadan Electricity Distribution Company (IBEDC) customers in Sagamu, Ogijo, Remo, and Ikenne.

She listed other projects also completed recently within the region to include a newly constructed control room and the installation of a T4 1X60MVA 132/33kV power transformer which was energised at the Sagamu 132/33kV Transmission Substation in June.

โ€Similarly, another T1 1X60MVA 132/33kV power transformer was recently installed and energised in May upon the completion of the new Oluewu 132/33kV Substation in Oyo State.

โ€The increase in transformers capacity means more power for IBEDC to off-take and distribute to its customers in Sagamu and environs, โ€she said