Kayode Oloko: The Steady Hand Behind Think Yoruba First Dangote Refinery Slashes Petrol Gantry Price to N1,175 Per Litre IllBliss: A Tenant Who Mistook Rent for Ownership – Lagos Will Never Be Yours “We Are Coming to Rob and Kidnap You All” – Chilling Notice Terrorises Mowe Residents Enugu NDC in Turmoil as Aspirants Allege N1 Billion Extortion, Pass Vote of No Confidence on Nwodo Ex-Ambassador Bode Sunmonu to Lead Olokola Free Trade Zone Technical Committee as Ondo Pushes Industrial Revolution Ondo State Set for Industrial Revolution as Dangote Unveils Nigeria’s Biggest Industrial Free Trade Zone UPDATE 🇳🇬🛥️💰: Billionaire Abdul Samad Rabiu Hosts Billionaire Femi Otedola and Friends on Luxury Yacht in Monaco Gathering
NEWS

Power Cut: Niger Republic Turns to Mega Solar Power Plant

November 28, 2023 3 min read

Niger has initiated the operation of its mega solar power plant, mitigating the power shortages brought about by Nigeria’s exit from its power sector.

Niger’s mega solar power plant is now operational, mitigating Niger’s 70% power loss.

Despite coup-related delays, the solar plant significantly improves power supply in Niger’s capital and other key towns.

The French Embassy warns of operational risks.

Following the July coup in Niger that deposed previous President Mohamed Bazoum, a fellow West African country, Nigeria chose to respond by suspending energy exports to the country.

This posed a significant issue in Niger’s power sector, considering that Nigeria supplied 70% of Niger’s electricity prior to the coup.

According to a report recently put out by the British news network, BBC, Niger has since then experienced cascading power outages.

However, Niger’s response was to focus on the solar project it had initiated a few years back.

The BBC’s report states, “The plant, built by a French consortium, was initiated in 2018 and inaugurated on 5 July this year.

French relations with the Nigerien junta have turned sour since the coup.

The plant has over 55,000 solar panels and can generate 30 megawatts of electricity.”

Its intended launch was set for August once Niger was able to connect the solar plant to its national electricity grid. However, the coup brought about a delay in its initiation.

According to Niger’s Energy Minister, Mahaman Moustapha Barke, Niger’s power supply has dramatically improved since the launch of the solar plant, particularly in the country’s capital and some other towns.

The project was also acknowledged by the French Embassy in Mali as it recognized the solar power’s launch but warned of operational risks. “It could not be finalized under the conditions initially planned,” as seen in the BBC’s report.

Niger’s energy minister indicated on Sunday that the technical staff that stayed behind made the completion of the solar power plant possible.

Niger’s coup consequences

The energy gap brought about by Nigeria’s withdrawal from Niger’s energy supply is hardly the only challenge brought about by international sanctions. Shortly after the Niger coup, the World Bank disclosed that it had halted disbursements to the country until further notice, with the exception of private-sector partnerships.

Furthermore, it was reported in August that a border closure between Nigeria and Niger had put the estimated annual $226.34 million trade between the two countries at risk of collapse.